Teesside GasPort is the world’s first dockside LNG vaporization
and natural gas receiving facility. Placed in service in February 2007,
Teesside GasPort delivers natural gas into the UK’s National Transmission
System (NTS) and provides access to National Balancing Point (NBP) markets.
Teesside GasPort can initially accommodate deliveries at a baseload rate
of up to 400 mmcf/d with peak rates of up to 600 mmcf/d. With on-site
nitrogen blending facilities, Teesside GasPort can accommodate virtually
any quality of LNG delivered and still meet stringent NTS standards.
As an example of the flexibility that Excelerate Energy’s GasPort
technology offers, Teesside GasPort was brought into service within 12
months of site selection and at a cost that is roughly 10% of a conventional
land-based LNG terminal with the same capabilities.
Key Information
Second operational LNG receiving facility
in the UK
Site selection to in-service date in 12 months
Low capital cost, high flexibility asset for LNG imports
Ability to handle peak imports of
up to 600 mmcf/d of natural gas
High Pressure gas arm incorporated
in design
Accommodates ship motions and incorporates “Quick Release”
Allows direct discharge from EBRV High Pressure Gas Manifold
Nitrogen blending with the capability
to delivery up to 5% N2
Dedicated jetty capable of accommodating
up to 150,900 m3 EBRVs